Utilities Industry |
Remark: Ice water pump oprates under lower load for a longer time period then estimated |
Installation time:December 2014 Project scope:Ice water pump, water-cooling pump, cooling tower fan supply to air conditioning compressor and water pumps for IDC – 5HP 30HP TECO motor pump Model:VR series x 3 Power supply:3Φ / 380V / 60Hz Method:motor VF control, constant temperature mode Installation agent:JJNET International Co., Ltd. Related documentation:Taipei Gas testing report Photos |
Financial Industry |
Remark: Actual saving rate matchs estimate saving range |
Installation time:October 2014 Project scope:Ice water pump to provide air conditioning in office area – 10HP TECO motor pump Model:VR series x 1 Power supply:3Φ / 220V / 60Hz Method:motor VF control, constant temperature mode Installation agent:Taiwan ForeverPower Tech. Co., Ltd. Photos |
Financial Industry |
Remark: Actual saving rate matchs estimate saving range |
Installation time:Oct.2014 Project scope:Office building air conditioning system scroll compressor Model: VR 2 Units Power supply:3ψ/380V/60Hz Method:Inverter stepless frequency control, constant refregant pressure control Photos |
行政大樓 Office Building |
Remark: Office environment oprates at constant temperature condition, low temperature deviation caused water pump operates long time at lower load, caused saving rate 5% ~ 15% higher then original estimated |
Installation time:July 2014 Project scope:Ice water pump to provide air conditioning to 6-floor office area – 30HP TECO motor pump Model:VR series x 1 Power supply:3Φ / 440V / 60Hz Method:motor VF control, constant temperature mode Photos |
Financial Industry |
Remark: Remark: Actual saving rate matchs estimate saving range |
Installation time:May 2014 Project scope:Ice water pump to provide air conditioning to office area – 20HP TECO motor pump Model:VR series x 1 Power supply: 3Φ / 380V / 60Hz Method:motor VF control, constant temperature mode Photos |
|
Remark: Ice water pump oprates under lower load for a longer time period then estimated |
Installation time:March 2011 Project scope:Ice water pump, water-cooling pump supplied to air conditioning compressor for whole plaza – 15HP 20HP 25HP TECO motor pump Model:VR series x 6 Power supply:3Φ / 380V / 60Hz Method:motor VF control, differential temperature mode Photos |
Supermarket |
Remark: Cooling tower pump oprates under lower load for a longer time period then estimated. Additional benefit is noise db low down to 63db from original 73db, avoid city government noise pollution fine. |
Installation time:May 2010 Project scope:Heat dissipation cooling tower supplied to store air conditioning – 5HP TECO motor Model:SES-VR series x 1 Power supply: 3Φ / 380V / 60Hz Method:motor VF control, constant temperature mode Photos |
Show room & office building |
Remark: Ice water pump oprates under lower load for a longer time period then estimated. This case customized with communication modular implemented for real time remote monitoring capability. |
Installation time:November 2008 Project scope:Ice water pump supplied to air conditioning in display center – 10HP Tatung motor pump Model:VR series x 2 Power supply:3Φ / 380V / 60Hz Method:motor VF control, constant water temperature mode Photos |
Financial Industry |
Remark: Air conditioner compressor oprates under lower load for a longer time period then estimated |
Installation time:April 2008 Project scope:Scroll compressor for air conditioning in 1st floor, 2nd floor office area – 7.5HP 10HP 15HP Mitsubishi motor Model:VR series x 8 Power supply:3Φ / 380V / 60Hz Method:Motor VF control, constant temperature mode Related documentation:Efficiency analysis graph Photos |
Financial Industry |
Remark: Ice water pump oprates under lower load for a longer time period then estimated |
Installation time:August 2007 Project scope:Ice water pump for air conditioning in office area – 20HP TECO motor pump Model:VR series x 1 Power supply:3Φ / 380V / 60Hz Method:Motor VF control, constant temperature mode Photos |
|
|